Forum Discussion

Ollie's avatar
Ollie
Brass Contributor
Feb 07, 2024
Solved

Project for the web - Recycle bin / Versioning

Hi,    Is there any facility in Project for the Web to track changes to a project or recover deleted items?    Ollie
  • Dale_HowardMVP's avatar
    Feb 07, 2024
    Oliver --

    There is no Recycle Bin for Project for the Web. The tool DOES offer a Task History feature, but this is only for individual tasks. Hope this helps.

Resources