Project Doubts (% complete)

%3CLINGO-SUB%20id%3D%22%5C%26quot%3Blingo-sub-3171455%5C%26quot%3B%22%20slang%3D%22%5C%26quot%3Ben-US%5C%26quot%3B%22%3EProject%20Doubts%20(%25%20complete)%26lt%3B%5C%2Flingo-sub%26gt%3B%3CLINGO-BODY%20id%3D%22%5C%26quot%3Blingo-body-3171455%5C%26quot%3B%22%20slang%3D%22%5C%26quot%3Ben-US%5C%26quot%3B%22%3E%3CP%3EHello%20Guys%2C%26nbsp%3B%26lt%3B%5C%2FP%26gt%3B%3C%2FP%3E%3CP%3EI'm%20new%20to%20the%20project%20application.%20I%20have%20been%20assigned%20a%20project%20schedule%20by%20my%20company.%26nbsp%3B%26lt%3B%5C%2FP%26gt%3B%3C%2FP%3E%3CP%3EI%20have%20somehow%20created%20the%20project%20schedule%20and%20assigned%20the%20tasks%20as%20manually%20scheduled.%26nbsp%3B%26lt%3B%5C%2FP%26gt%3B%3C%2FP%3E%3CP%3EI%20have%205%20tasks%20in%20my%20project%20and%20I%20have%20finished%202%20of%20them.%20I%20have%20also%20added%20%25%20complete%20field%20and%20when%20I'm%20updating%20the%20status%20of%20the%20task%20to%20100%25%20for%20subtasks%2C%20everything%20is%20fine.%26nbsp%3B%26lt%3B%5C%2FP%26gt%3B%3C%2FP%3E%3CP%3E%3CSTRONG%3EProblem%20statement%3A%26lt%3B%5C%2FSTRONG%26gt%3B%26lt%3B%5C%2FP%26gt%3B%3C%2FSTRONG%3E%3C%2FP%3E%3CP%3EAfter%20setting%20the%20status%20of%20the%20tasks%20to%20100%25%20in%202%20phases%2C%20my%20overall%20%25%20complete%20is%20going%20to%2061%25.%20But%20I%20have%20defined%205%20phases%20in%20the%20project%20schedule%20and%203%20of%20them%20haven't%20even%20started.%20So%20just%20wanted%20to%20know%20how%20it%20is%20calculated%20as%2060%25%3F%26lt%3B%5C%2FP%26gt%3B%3C%2FP%3E%3CP%3E%26nbsp%3B%26lt%3B%5C%2FP%26gt%3B%3C%2FP%3E%3CP%3EPlease%20do%20help%20me%20with%20this%20issue.%26lt%3B%5C%2FP%26gt%3B%3C%2FP%3E%3CP%3E%26nbsp%3B%26lt%3B%5C%2FP%26gt%3B%26lt%3B%5C%2Flingo-body%26gt%3B%3C%2FP%3E%3C%2FLINGO-BODY%3E%3C%2FLINGO-SUB%3E%3CLINGO-SUB%20id%3D%22lingo-sub-3171455%22%20slang%3D%22en-US%22%3EProject%20Doubts%20(%25%20complete)%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-3171455%22%20slang%3D%22en-US%22%3E%3CP%3EHello%20Guys%2C%26nbsp%3B%3C%2FP%3E%3CP%3EI'm%20new%20to%20the%20project%20application.%20I%20have%20been%20assigned%20a%20project%20schedule%20by%20my%20company.%26nbsp%3B%3C%2FP%3E%3CP%3EI%20have%20somehow%20created%20the%20project%20schedule%20and%20assigned%20the%20tasks%20as%20manually%20scheduled.%26nbsp%3B%3C%2FP%3E%3CP%3EI%20have%205%20tasks%20in%20my%20project%20and%20I%20have%20finished%202%20of%20them.%20I%20have%20also%20added%20%25%20complete%20field%20and%20when%20I'm%20updating%20the%20status%20of%20the%20task%20to%20100%25%20for%20subtasks%2C%20everything%20is%20fine.%26nbsp%3B%3C%2FP%3E%3CP%3E%3CSTRONG%3EProblem%20statement%3A%3C%2FSTRONG%3E%3C%2FP%3E%3CP%3EAfter%20setting%20the%20status%20of%20the%20tasks%20to%20100%25%20in%202%20phases%2C%20my%20overall%20%25%20complete%20is%20going%20to%2061%25.%20But%20I%20have%20defined%205%20phases%20in%20the%20project%20schedule%20and%203%20of%20them%20haven't%20even%20started.%20So%20just%20wanted%20to%20know%20how%20it%20is%20calculated%20as%2060%25%3F%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3EPlease%20do%20help%20me%20with%20this%20issue.%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3C%2FLINGO-BODY%3E
Occasional Visitor

Hello Guys, 

I'm new to the project application. I have been assigned a project schedule by my company. 

I have somehow created the project schedule and assigned the tasks as manually scheduled. 

I have 5 tasks in my project and I have finished 2 of them. I have also added % complete field and when I'm updating the status of the task to 100% for subtasks, everything is fine. 

Problem statement:

After setting the status of the tasks to 100% in 2 phases, my overall % complete is going to 61%. But I have defined 5 phases in the project schedule and 3 of them haven't even started. So just wanted to know how it is calculated as 60%?

 

Please do help me with this issue.

 

1 Reply
Project Doubts --

The % Complete field literally means % of Duration Complete. The formula used to calculate % Complete is Actual Duration/Duration x 100%. Duration represents the total time span of the project, while Actual Duration represents how much of the time span has been "used up" or completed.

So, when you see the % Complete value of 61% for your project, this indicates that you have "used up" 61% of the time span allotted to complete the project. Hope this helps.