Forum Discussion
Mohit7799
Feb 16, 2022Copper Contributor
Project Doubts (% complete)
Hello Guys, I'm new to the project application. I have been assigned a project schedule by my company. I have somehow created the project schedule and assigned the tasks as manually scheduled. ...
Feb 16, 2022
Project Doubts --
The % Complete field literally means % of Duration Complete. The formula used to calculate % Complete is Actual Duration/Duration x 100%. Duration represents the total time span of the project, while Actual Duration represents how much of the time span has been "used up" or completed.
So, when you see the % Complete value of 61% for your project, this indicates that you have "used up" 61% of the time span allotted to complete the project. Hope this helps.
The % Complete field literally means % of Duration Complete. The formula used to calculate % Complete is Actual Duration/Duration x 100%. Duration represents the total time span of the project, while Actual Duration represents how much of the time span has been "used up" or completed.
So, when you see the % Complete value of 61% for your project, this indicates that you have "used up" 61% of the time span allotted to complete the project. Hope this helps.