Planning activity in different days

%3CLINGO-SUB%20id%3D%22lingo-sub-1648547%22%20slang%3D%22en-US%22%3EPlanning%20activity%20in%20different%20days%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-1648547%22%20slang%3D%22en-US%22%3E%3CP%3E%3CSPAN%3EHello!%20I'm%20new%20here%20and%20I%20have%20one%20question%20about%20planning%20activity%20in%20Microsoft%20Project.%20For%20example%20the%20activity%20start%20on%2001%2F09%2C%20the%20following%20day%20is%20on%2005%2F09%20and%20the%20end%20is%20on%2025%2F09.%20How%20can%20I%20represent%20on%20Microsoft%20Project%3F%20Because%20if%20I%20write%3A%20start%2001%2F09%20and%20finish%2025%2F09%2C%20the%20software%20counts%2024%20days..but%20this%20is%20not%20right%20because%20the%20duration%20is%203%20days.%20Someone%20can%20help%20me%2C%20please%3F%3C%2FSPAN%3E%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3C%2FLINGO-BODY%3E%3CLINGO-LABS%20id%3D%22lingo-labs-1648547%22%20slang%3D%22en-US%22%3E%3CLINGO-LABEL%3EProject%3C%2FLINGO-LABEL%3E%3C%2FLINGO-LABS%3E%3CLINGO-SUB%20id%3D%22lingo-sub-1660797%22%20slang%3D%22en-US%22%3ERe%3A%20Planning%20activity%20in%20different%20days%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-1660797%22%20slang%3D%22en-US%22%3E%3CP%3EHello%26nbsp%3B%3CA%20href%3D%22https%3A%2F%2Ftechcommunity.microsoft.com%2Ft5%2Fuser%2Fviewprofilepage%2Fuser-id%2F787174%22%20target%3D%22_blank%22%3E%40Dado44%3C%2FA%3E%26nbsp%3B%2C%3C%2FP%3E%0A%3CP%3EAre%20you%20looking%20to%20do%20something%20like%20this%20with%20split%20tasks%3C%2FP%3E%0A%3CP%3E%3CSPAN%20class%3D%22lia-inline-image-display-wrapper%20lia-image-align-left%22%20image-alt%3D%22splittask.png%22%20style%3D%22width%3A%20999px%3B%22%3E%3CIMG%20src%3D%22https%3A%2F%2Ftechcommunity.microsoft.com%2Ft5%2Fimage%2Fserverpage%2Fimage-id%2F217987i636653C63D7DE4A6%2Fimage-size%2Flarge%3Fv%3D1.0%26amp%3Bpx%3D999%22%20title%3D%22splittask.png%22%20alt%3D%22splittask.png%22%20%2F%3E%3C%2FSPAN%3E%3C%2FP%3E%0A%3CP%3E%26nbsp%3B%3C%2FP%3E%0A%3CP%3E%26nbsp%3B%3C%2FP%3E%0A%3CP%3E%26nbsp%3B%3C%2FP%3E%0A%3CP%3E%26nbsp%3B%3C%2FP%3E%0A%3CP%3E%26nbsp%3B%3C%2FP%3E%0A%3CP%3E%26nbsp%3B%3C%2FP%3E%0A%3CP%3E%26nbsp%3B%3C%2FP%3E%0A%3CP%3E%26nbsp%3B%3C%2FP%3E%0A%3CP%3E%3CA%20href%3D%22https%3A%2F%2Fsupport.microsoft.com%2Fen-us%2Foffice%2Fsplit-a-task-20c8581b-6266-45e3-af54-cc7c3b10deca%22%20target%3D%22_blank%22%20rel%3D%22noopener%20noopener%20noreferrer%20noopener%20noreferrer%22%3Ehttps%3A%2F%2Fsupport.microsoft.com%2Fen-us%2Foffice%2Fsplit-a-task-20c8581b-6266-45e3-af54-cc7c3b10deca%3C%2FA%3E%3C%2FP%3E%0A%3CP%3E%26nbsp%3B%3C%2FP%3E%0A%3CP%3EPaul%3C%2FP%3E%3C%2FLINGO-BODY%3E
Highlighted
New Contributor

Hello! I'm new here and I have one question about planning activity in Microsoft Project. For example the activity start on 01/09, the following day is on 05/09 and the end is on 25/09. How can I represent on Microsoft Project? Because if I write: start 01/09 and finish 25/09, the software counts 24 days..but this is not right because the duration is 3 days. Someone can help me, please?

 

2 Replies
Highlighted
Best Response confirmed by Dado44 (New Contributor)
Solution

Hello @Dado44 ,

Are you looking to do something like this with split tasks

splittask.png

 

 

 

 

 

 

 

 

https://support.microsoft.com/en-us/office/split-a-task-20c8581b-6266-45e3-af54-cc7c3b10deca

 

Paul

Highlighted

@Paul Mather thanks a lot!