Forum Discussion
Dado44
Sep 09, 2020Copper Contributor
Planning activity in different days
Hello! I'm new here and I have one question about planning activity in Microsoft Project. For example the activity start on 01/09, the following day is on 05/09 and the end is on 25/09. How can I rep...
- Sep 12, 2020
Hello Dado44 ,
Are you looking to do something like this with split tasks
https://support.microsoft.com/en-us/office/split-a-task-20c8581b-6266-45e3-af54-cc7c3b10deca
Paul
Paul_Mather
Sep 12, 2020MVP
Hello Dado44 ,
Are you looking to do something like this with split tasks
https://support.microsoft.com/en-us/office/split-a-task-20c8581b-6266-45e3-af54-cc7c3b10deca
Paul
- Dado44Sep 16, 2020Copper Contributor
Paul_Mather thanks a lot!