Forum Discussion
James_Price
Jun 15, 2021Brass Contributor
MS Project timeline labels are wrong...
Hi team
In MS Project Gantt, when I tick on the 'Use fiscal year' box, the labels change to the previous year. And this is exactly what's happening in the Timeline view. The starting task is 8 Jan 2021, but the first label is Feb 20. However, in the Timeline view there is no 'Use fiscal year' box to untick.
Any ideas on what I can do?
Many thanks
James
- James -- Did you set the starting month of the fiscal year on the Schedule page of the Project Options dialog? If so, did you select the checkbox named Use Starting Year for FY Numbering? Please let us know and we will try to help you.
10 Replies
Sort By
- James -- Did you set the starting month of the fiscal year on the Schedule page of the Project Options dialog? If so, did you select the checkbox named Use Starting Year for FY Numbering? Please let us know and we will try to help you.
- James_PriceBrass ContributorPerfect. Thanks for this Dale
James- James_PriceBrass ContributorHi Dale
Something strange happened in the timeline which I missed. Jan to Mar became correct showing Jan21 to Mar21. Then it shows Apr22 to Dec22 and then correctly shows Jan22 to Dec22. The labels above the Gantt are fine.
Any thoughts?
Many thanks
James