Forum Discussion
James_Price
Jun 14, 2021Brass Contributor
MS Project timeline labels are wrong...
Hi team In MS Project Gantt, when I tick on the 'Use fiscal year' box, the labels change to the previous year. And this is exactly what's happening in the Timeline view. The starting task is 8 Jan...
- Jun 15, 2021James -- Did you set the starting month of the fiscal year on the Schedule page of the Project Options dialog? If so, did you select the checkbox named Use Starting Year for FY Numbering? Please let us know and we will try to help you.
Jun 15, 2021
James -- Did you set the starting month of the fiscal year on the Schedule page of the Project Options dialog? If so, did you select the checkbox named Use Starting Year for FY Numbering? Please let us know and we will try to help you.
- James_PriceJun 15, 2021Brass ContributorPerfect. Thanks for this Dale
James- James_PriceJun 16, 2021Brass ContributorHi Dale
Something strange happened in the timeline which I missed. Jan to Mar became correct showing Jan21 to Mar21. Then it shows Apr22 to Dec22 and then correctly shows Jan22 to Dec22. The labels above the Gantt are fine.
Any thoughts?
Many thanks
James- Jun 18, 2021James -- Would you please provide a screenshot or two so that I can see what is going on? That would help. Thanks!