Ms project ressource leveling automatic split

Copper Contributor

Hello, 

 

I am trying to use the feature of Ms project that automatically split remaining work to do with a resource.

Here is a very basic example not leveled yet: 

sara1201_0-1703005013176.png

  • start date of test 1 is 14/12/23
  • start date of test 2 is 07/12/23
  • priority of test 1 (900) is higher than test 2 (800)

I would like test2 to start before and then split the remaining work when we need to start test 1

I did the following things: 

  • Check box in leveling options  "leveling can create splits in remaining work" is checked 
  • Column "Leveling can split" ies set to Yes

However when I do leveling it does not split any task to optimize the duration of the project.

here is the output when I press Level All

sara1201_0-1703005340459.png

 

Could you help me ? 

 

4 Replies

@sara1201 

Hi Sarah.

Did you try this configuration of the Resource Leveling options?

 

Configuración nivelación.png

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Ignacio

@Ignacio_Martin 

Hello, thank you for your reply.

Yes, but it still does not split the remaining task.

sara1201_0-1703059879571.png

 

best response confirmed by sara1201 (Copper Contributor)
Solution
Hi Sara.
If the Task type in test 2 is "Fixed Duration", change it to "Fixed Units" or "Fixed Work" (double click on the task > Advanced tab)
Likewise, try selecting "As Soon As Possible" option in Test2 Constraint type (double click on the task > Advanced tab), because the last image you attached shows a constraint.
N. Option "Leveling can adjust individual assignments on a task", in this case it does not need to be selected. It can be applied when there is more than one assignment (resource) in the same task.
I hope I've helped.
Ignacio
Hello Ignacio,
It worked now ! thank you so much !
1 best response

Accepted Solutions
best response confirmed by sara1201 (Copper Contributor)
Solution
Hi Sara.
If the Task type in test 2 is "Fixed Duration", change it to "Fixed Units" or "Fixed Work" (double click on the task > Advanced tab)
Likewise, try selecting "As Soon As Possible" option in Test2 Constraint type (double click on the task > Advanced tab), because the last image you attached shows a constraint.
N. Option "Leveling can adjust individual assignments on a task", in this case it does not need to be selected. It can be applied when there is more than one assignment (resource) in the same task.
I hope I've helped.
Ignacio