MS Project for the WEB - Some simple questions

Hi,

 

I have a few questions related to MS Project for the Web. I have a licence and have created a few projects to test the functionality as my team is planning to use MS Project for the WEB as our PM tool moving forward. We have 5 PMs in our team.

 

  1. I have created projects and a roadmap and can see them in my Project Home (project.microsoft.home). If my other 4 colleagues get a license and start creating projects will they see only their projects in their specific Project Home or is there a way to combine all projects in one Project Home so our team can see all projects?
  2. I have also connect Power BI to my projects and used the default portfolio template which automatically pulls in my projects data and shows a variety tabbed views which is really useful. If my other 4 colleagues create projects can I also tie them to the portfolio template so all project data is available for the analytics? Is there a way to do this, could you point me in the right direction?

 

Sorry for the basic questions but I want to make sure it works for the team before we move forward. 

 

Thanks

Eddie

4 Replies

  • Eddie --

    To answer your questions:

    1. Each PM will only be able to see his/her own projects on their Project Home page.
    2. Yes, you can pull all of your organization's projects into Power BI reports, including a portfolio report.

    Hope this helps.
      • RodFromm's avatar
        RodFromm
        Iron Contributor

        Eddie_Morris You can grant access to a Project for the Web project with another PM and it will show up on the Project Home (default) page under the "Shared with me " tab.  When you share the project  you have the ability to define the permissions granted: Read, Write, Delete, Append, etc.