Forum Discussion
BKirby88
Mar 30, 2023Copper Contributor
Lag settings
I have two calendars set up one with a standard week & another weekends only. I want to add a lag for a task which is a weekend activity with the standard week calendar and not the weekend only calendar. Is this possible?
4 Replies
- Bkirby88 --
If you want the task to occur on a weekend, you need to apply the weekend work calendar to the task. Does that help? If not, please follow up with additional questions. Thanks!- BKirby88Copper ContributorHi,
Not quite.
For example:
Task 1 - Issue purchase order to supplier ( Weekday calendar )
Task 2 - Complete work ( Weekend working ). I want to add a 60day Leadtime from the purchase order until the start of task 2 but it used the weekend working calendar, but the 60day lead time is during the normal working week.- PlannersPlaceBrass Contributor
The lag between Tasks 1 & 2 should be 24 days.
60 days in Standard calendar equals 12 weeks. 12 weeks in Weekend calendar is 12 x 2 days = 24 days.
=jerome
https://youtube.com/@PlannersPlace