Forum Discussion
BKirby88
Mar 30, 2023Copper Contributor
Lag settings
I have two calendars set up one with a standard week & another weekends only. I want to add a lag for a task which is a weekend activity with the standard week calendar and not the weekend only calen...
Mar 30, 2023
Bkirby88 --
If you want the task to occur on a weekend, you need to apply the weekend work calendar to the task. Does that help? If not, please follow up with additional questions. Thanks!
If you want the task to occur on a weekend, you need to apply the weekend work calendar to the task. Does that help? If not, please follow up with additional questions. Thanks!
- BKirby88Mar 30, 2023Copper ContributorHi,
Not quite.
For example:
Task 1 - Issue purchase order to supplier ( Weekday calendar )
Task 2 - Complete work ( Weekend working ). I want to add a 60day Leadtime from the purchase order until the start of task 2 but it used the weekend working calendar, but the 60day lead time is during the normal working week.- PlannersPlaceMar 30, 2023Brass Contributor
The lag between Tasks 1 & 2 should be 24 days.
60 days in Standard calendar equals 12 weeks. 12 weeks in Weekend calendar is 12 x 2 days = 24 days.
=jerome
https://youtube.com/@PlannersPlace
- Mar 30, 2023BKirby88 --
I can confirm the odd behavior you are seeing. Yes, the Lag time amount is measured according to the Weekend calendar schedule and not the schedule of the Standard calendar. I would recommend that you do the following:
1. Break the dependency between task IDs #1 and #2.
2. Create a new task ID #2 named something like Wait for Delivery and set the Duration to 60d.
2. Link task IDs #1-3 with a Finish-to-Start dependency.
I think the above will solve your problem nicely. Hope this helps.