Integration MS Project and Power BI

Copper Contributor

Greetings,

 

Can someone clarify the above-mentioned subject: What is the current situation?

 

Thx

2 Replies
best response confirmed by Javanshir (Copper Contributor)
Solution

Hello @Javanshir ,

Is this for MS Project Desktop / Project Professional and Power BI? If so, that is not possible directly. You could look at exporting the Project data from Project Desktop into Excel and using the Excel file as a data source in Power BI.

Paul

Thank you - You've confirmed my way