Forum Discussion

Javanshir's avatar
Javanshir
Copper Contributor
Sep 11, 2023
Solved

Integration MS Project and Power BI

Greetings,   Can someone clarify the above-mentioned subject: What is the current situation?   Thx
  • Paul_Mather's avatar
    Sep 11, 2023

    Hello Javanshir ,

    Is this for MS Project Desktop / Project Professional and Power BI? If so, that is not possible directly. You could look at exporting the Project data from Project Desktop into Excel and using the Excel file as a data source in Power BI.

    Paul