Feb 03 2023 11:15 AM
I created a new schedule and set the durations to give me the correct Start and Finish Dates, however I forgot to change the calendar at the beginning from the standard default, which is 5 days a week. I need to change the calendar to 7 days a week without altering the start and finish. How can I update the calendar to increase the durations and not the Start / Finish Dates?
Feb 03 2023 12:50 PM
It kinda sounds like you want to do the schedule instead of letting Project do what it does best. Hopefully you are NOT also using manual scheduling. If you are then why use Project, Excel would be easier.
But to answer your question, how did you enter the duration values, hours or days? If your 7 day workweek calendar still has the default 8 hour workday (8:00 AM to 5:00 PM with 1 hour lunch break), then adding the 2 extra days will effectively add 2 days or 16 hours which you will have to add to each duration value. If you have custom work hours in your 7 day calendar, then you will have to add the appropriate amount.
You will have to do all this manually, there is no setting that will automatically make the adjustment for you.
Hope this helps.
John
Feb 03 2023 02:46 PM
Feb 03 2023 03:38 PM
Feb 06 2023 04:00 PM - edited Feb 06 2023 04:13 PM
Hello
In response your request to keep the scheduled dates after changing project calendar, you can try this experimental procedure, following the steps below:
In the initial project file, and before changing the calendar from 5 to 7 days
Note.- It must be manually adjusted, increasing or reducing the lag of the links other than 0 days, when the successor task does not coincide with the initial dates of the 5-day calendar.
Select: Baseline 5, under Gantt Chart Format / Bar Styles / Baseline, to hide the Baseline 5 bar on the Gantt.
Note: Other variables such as Task type, other Constraints date, Task calendars, Resource work, Costs, etc. could influence the result sought, and would require a more exhaustive analysis.
I hope you find it useful.
Ignacio Martín