Forum Discussion
How to update Project Calendar & Keep Start / Finish Dates the same
Hello
In response your request to keep the scheduled dates after changing project calendar, you can try this experimental procedure, following the steps below:
In the initial project file, and before changing the calendar from 5 to 7 days
- Make backup copy of the file
- Establish a baseline that is free, such as Baseline 5, for example, which will serve as visual reference in the Gantt, by selecting: (Menu / Project / Schedule / Establish Baseline...Entire project, and OK)
- Select Baseline 5, in: (Gantt Chart Format / Bar Styles / Baseline)
- Hide, if not already, the Project Summary Task, in: (Gantt Chart Format / Show or Hide)
- Shows, if not, the column % Complete
- Insert a column of a custom text field into the table, such as Text1, for example
- Copy column % Complete to Text1
- Copies at the same time to the clipboard (memory), the contiguous columns, Start and Finish
- Modify your calendar from 5 to 7 working days per week
- Select all the tasks of the project (click upper left corner of the table)
- Select these three options at once: Percet complete = 0%, Duration = 0 day, and Schedule Mode = Manually Scheduled; in the General tab, through: (Menu / Task / Properties / Information, and OK)
- Pastes the Start and Finish columns from the clipboard (in memory), onto those columns
- Copy and Paste the column Text1 in % Complete
- Select all tasks of the project (click upper left corner of the table)
- Select Auto Schedule option, in Menu / Task / Tasks
Note.- It must be manually adjusted, increasing or reducing the lag of the links other than 0 days, when the successor task does not coincide with the initial dates of the 5-day calendar.
Select: Baseline 5, under Gantt Chart Format / Bar Styles / Baseline, to hide the Baseline 5 bar on the Gantt.
Note: Other variables such as Task type, other Constraints date, Task calendars, Resource work, Costs, etc. could influence the result sought, and would require a more exhaustive analysis.
I hope you find it useful.
Ignacio Martín