Jun 23 2022 11:18 PM
Hi
I am trying to have two tasks start on same day both linked to each other. So this is what I tried:
Two task example
Task A 06/23/2022 06/23/2022 1 day
Task B 06/23/2022 06/23/2022 1 day
Task C 06/23/2022 06/23/2022 1 day
What I initially did is I copied the end date of the first and did a paste special as object to the start of Task B and that worked. I did even have the predecessors too.
But when I tried to add more that technique didn't worked out.
The only time I can have all tasks start on the same day / date is when I do not link them or remove predecessors
Any advise will be much appreciated.
Thanks,
Jun 24 2022 01:01 AM
SolutionHello @ThePM-CA ,
What about changing the relationship type to Start to Start:
To do this, either:
Or:
I hope that helps
Paul
Jun 24 2022 01:01 AM
SolutionHello @ThePM-CA ,
What about changing the relationship type to Start to Start:
To do this, either:
Or:
I hope that helps
Paul