Forum Discussion

ThePM-CA's avatar
ThePM-CA
Brass Contributor
Jun 24, 2022
Solved

How to have two tasks start on same day

Hi    I am trying to have two tasks start on same day both linked to each other. So this is what I tried:   Two task example    Task A    06/23/2022  06/23/2022  1 day    Task B    06/23/2022  ...
  • Paul_Mather's avatar
    Jun 24, 2022

    Hello ThePM-CA ,

    What about changing the relationship type to Start to Start:

    To do this, either:

    • Double click the task and use the Task Information window then on the Predecessors tab change the Type as seen below:

    Or:

    • Click in the Predecessors field, press F2 to put the cell in edit mode then type SS after the task ID:

    I hope that helps

    Paul

Resources