How to have two tasks start on same day
Hi I am trying to have two tasks start on same day both linked to each other. So this is what I tried: Two task example Task A 06/23/2022 06/23/2022 1 day Task B 06/23/2022 ...
- Jun 24, 2022
Hello ThePM-CA ,
What about changing the relationship type to Start to Start:
To do this, either:
- Double click the task and use the Task Information window then on the Predecessors tab change the Type as seen below:
Or:
- Click in the Predecessors field, press F2 to put the cell in edit mode then type SS after the task ID:
I hope that helps
Paul
Paul_Mather
Jun 24, 2022MVP
Hello ThePM-CA ,
What about changing the relationship type to Start to Start:
To do this, either:
- Double click the task and use the Task Information window then on the Predecessors tab change the Type as seen below:
Or:
- Click in the Predecessors field, press F2 to put the cell in edit mode then type SS after the task ID:
I hope that helps
Paul
- ThePM-CAJun 24, 2022Brass ContributorThank you Paul it worked