Dec 16 2023 01:28 PM
Dec 17 2023 08:54 AM
SolutionBy default the Duration field is in working days so I don't understand what you mean by "calendar days column". There is no "calendar days" field displayed as a column in Project.
If you want the Duration field to be in calendar days, enter the value as "Xed", which means, "X" elapsed (calendar) days.
If you want to have two fields shown as columns next to each other in the view, one the default Duration and the other a custom Duration field (e.g. Duration1), you can use the following construct:
John
John
Dec 17 2023 12:51 PM
Dec 17 2023 01:08 PM
Dec 17 2023 08:54 AM
SolutionBy default the Duration field is in working days so I don't understand what you mean by "calendar days column". There is no "calendar days" field displayed as a column in Project.
If you want the Duration field to be in calendar days, enter the value as "Xed", which means, "X" elapsed (calendar) days.
If you want to have two fields shown as columns next to each other in the view, one the default Duration and the other a custom Duration field (e.g. Duration1), you can use the following construct:
John
John