Forum Discussion

Underbudget007's avatar
Underbudget007
Copper Contributor
Dec 16, 2023
Solved

How can I add "working days" next to calendar days column in MS project?

Hi, How can I add "working days" next to calendar days column in MS project?
  • John-project's avatar
    Dec 17, 2023

    Underbudget007

    By default the Duration field is in working days so I don't understand what you mean by "calendar days column". There is no "calendar days" field displayed as a column in Project.

     

    If you want the Duration field to be in calendar days, enter the value as "Xed", which means, "X" elapsed (calendar) days.

     

    If you want to have two fields shown as columns next to each other in the view, one the default Duration and the other a custom Duration field (e.g. Duration1), you can use the following construct:

    John

     

    John

Resources