Hi can anyone suggest me.......how to create sprint type task level view in project online?

%3CLINGO-SUB%20id%3D%22lingo-sub-2655946%22%20slang%3D%22en-US%22%3EHi%20can%20anyone%20suggest%20me.......how%20to%20create%20sprint%20type%20task%20level%20view%20in%20project%20online%3F%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-2655946%22%20slang%3D%22en-US%22%3E%3CP%3EI%20want%20to%20make%20it%20as%20group%20by%20sprint.%20But%20in%20project%20online%20i%20am%20not%20able%20to%20find%20sprint%20column%3C%2FP%3E%3CP%3Eex%3A%20sprint%201%3C%2FP%3E%3CP%3E%26nbsp%3B%20%26nbsp%3B%20%26nbsp%3B%20%26nbsp%3B%20%26nbsp%3B%20Task%20name%3C%2FP%3E%3CP%3E%26nbsp%3B%20%26nbsp%3B%20%26nbsp%3B%20sprint%202%3C%2FP%3E%3CP%3E%26nbsp%3B%20%26nbsp%3B%20%26nbsp%3B%20%26nbsp%3B%20%26nbsp%3B%20%26nbsp%3BTask%20name%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3E%3CSPAN%20class%3D%22lia-inline-image-display-wrapper%20lia-image-align-inline%22%20image-alt%3D%22Anil_kumar_0-1629205719241.png%22%20style%3D%22width%3A%20400px%3B%22%3E%3CIMG%20src%3D%22https%3A%2F%2Ftechcommunity.microsoft.com%2Ft5%2Fimage%2Fserverpage%2Fimage-id%2F303733iD3A48F9B8DDC195E%2Fimage-size%2Fmedium%3Fv%3Dv2%26amp%3Bpx%3D400%22%20role%3D%22button%22%20title%3D%22Anil_kumar_0-1629205719241.png%22%20alt%3D%22Anil_kumar_0-1629205719241.png%22%20%2F%3E%3C%2FSPAN%3E%3C%2FP%3E%3CP%3E%3CSPAN%20class%3D%22lia-inline-image-display-wrapper%20lia-image-align-inline%22%20image-alt%3D%22Anil_kumar_1-1629205787143.png%22%20style%3D%22width%3A%20400px%3B%22%3E%3CIMG%20src%3D%22https%3A%2F%2Ftechcommunity.microsoft.com%2Ft5%2Fimage%2Fserverpage%2Fimage-id%2F303734i4A51C1BD429FB6B8%2Fimage-size%2Fmedium%3Fv%3Dv2%26amp%3Bpx%3D400%22%20role%3D%22button%22%20title%3D%22Anil_kumar_1-1629205787143.png%22%20alt%3D%22Anil_kumar_1-1629205787143.png%22%20%2F%3E%3C%2FSPAN%3E%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3CP%3E%26nbsp%3B%3C%2FP%3E%3C%2FLINGO-BODY%3E%3CLINGO-LABS%20id%3D%22lingo-labs-2655946%22%20slang%3D%22en-US%22%3E%3CLINGO-LABEL%3EOnline%3C%2FLINGO-LABEL%3E%3CLINGO-LABEL%3EProject%3C%2FLINGO-LABEL%3E%3CLINGO-LABEL%3EProject%20Server%3C%2FLINGO-LABEL%3E%3C%2FLINGO-LABS%3E%3CLINGO-SUB%20id%3D%22lingo-sub-2669486%22%20slang%3D%22en-US%22%3ERe%3A%20Hi%20can%20anyone%20suggest%20me.......how%20to%20create%20sprint%20type%20task%20level%20view%20in%20project%20online%3F%3C%2FLINGO-SUB%3E%3CLINGO-BODY%20id%3D%22lingo-body-2669486%22%20slang%3D%22en-US%22%3EAnil_kumar%20--%3CBR%20%2F%3E%3CBR%20%2F%3EI%20regret%20to%20tell%20you%20that%20none%20of%20the%20Sprint-related%20columns%20in%20Microsoft%20Project%20are%20available%20for%20inclusion%20in%20Project%20Web%20App%20views.%20They%20are%20local%20to%20Microsoft%20Project%20only.%20Sorry.%3C%2FLINGO-BODY%3E
Occasional Contributor

I want to make it as group by sprint. But in project online i am not able to find sprint column

ex: sprint 1

          Task name

      sprint 2

           Task name

 

Anil_kumar_0-1629205719241.png

Anil_kumar_1-1629205787143.png

 

 

2 Replies
Anil_kumar --

I regret to tell you that none of the Sprint-related columns in Microsoft Project are available for inclusion in Project Web App views. They are local to Microsoft Project only. Sorry.
No worries, thank you for ur reply Dale Howard. Yes , I guess so.......I am also searching for the blogs. I couldn't find any thing. If any one found the solution to this......Please try to post .