Forum Discussion
Anil_kumar
Aug 17, 2021Brass Contributor
Hi can anyone suggest me.......how to create sprint type task level view in project online?
I want to make it as group by sprint. But in project online i am not able to find sprint column ex: sprint 1 Task name sprint 2 Task name
Aug 20, 2021
Anil_kumar --
I regret to tell you that none of the Sprint-related columns in Microsoft Project are available for inclusion in Project Web App views. They are local to Microsoft Project only. Sorry.
I regret to tell you that none of the Sprint-related columns in Microsoft Project are available for inclusion in Project Web App views. They are local to Microsoft Project only. Sorry.
Anil_kumar_Anakala
Aug 22, 2021Tin Contributor
No worries, thank you for ur reply Dale Howard. Yes , I guess so.......I am also searching for the blogs. I couldn't find any thing. If any one found the solution to this......Please try to post .