Excluding Tasks from Critical Path Calculation
Hi,
I have a detailed program schedule with following hierarchy
Work Packages,
Sub Work packages,
WBS tasks
Milestones
There are about 15 work package and the structure repeats for every work package.
One of the last work packages has a Go-Live milestone.
WBS Tasks are linked across different work packages to create a path from start to Go-Live
Now if I plot the critical path, I get a huge list of small WBS tasks. This is good for actioning, but for reporting to executives, this is of little value.
Executives want to see critical path at Work Package level, Sub-Work Package level and milestones level.
Is there a way to select which tasks would be included / excluded into critical path calculation ?
It's important to note that predecessors are identified at WBS task levels, not at sub-work package or work package level.
If I exclude, WBS list from critical path calculation (I am assuming, I can), how does the linkages precipitate up to summary tasks ?