Forum Discussion
sshaffery
Oct 12, 2022Copper Contributor
Desktop Project will not Import to Project Online
Hello,
I am having an issue where some of my desktop projects are not importing to Project Online. Some files imported without issues, but others will not. I saw an earlier post about this but there was no answer on how to fix the issue, just that it was fixed. Any direction or assistance is appreciated.
Desktop Version: Microsoft® Project® Online Desktop Client MSO (Version 2202 Build 16.0.14931.20704) 64-bit
Message: Correlation ID: 1328838d-274b-43bd-a20f-42e4d4671e45
9 Replies
- John-projectSilver Contributor
I don't have Project Online but from your version description it looks like your installation hasn't been updated for some time. I suggest you check for updates and install them.
Joh
- sshafferyCopper ContributorI think I figured out my issue so I am posting incase someone else has the same problem. The files that would not load all had Baselines built in. I exported just the task data out to excel, reimported into project without the baseline. Now the file loads into Project Online without issue.
- sshaffery --
Your situation is mighty odd. I was able to successfully import a project containing a baseline into Project for the Web (application to which you refer as "Project Online"). After the import, a dialog reported to me that baselines were removed from the project. So, you SHOULD be able to import baselined projects into Project for the Web, except the baseline will be removed during the import process.
Out of curiosity, what happens if you do the following:
1. Open any project that has been baselined in Microsoft Project.
2. Clear any existing baselines.
3. Click File > Save As and save the project using an alternate name for the import process only.
4. Import the project into Project for the Web.
Do you still get the import error that you reported previously? Please let us know. Thanks!