Desktop Project will not Import to Project Online
Hello, I am having an issue where some of my desktop projects are not importing to Project Online. Some files imported without issues, but others will not. I saw an earlier post about this but...
John-project
Oct 12, 2022Silver Contributor
I don't have Project Online but from your version description it looks like your installation hasn't been updated for some time. I suggest you check for updates and install them.
Joh
- sshafferyOct 12, 2022Copper ContributorI think I figured out my issue so I am posting incase someone else has the same problem. The files that would not load all had Baselines built in. I exported just the task data out to excel, reimported into project without the baseline. Now the file loads into Project Online without issue.
- Oct 12, 2022sshaffery --
Your situation is mighty odd. I was able to successfully import a project containing a baseline into Project for the Web (application to which you refer as "Project Online"). After the import, a dialog reported to me that baselines were removed from the project. So, you SHOULD be able to import baselined projects into Project for the Web, except the baseline will be removed during the import process.
Out of curiosity, what happens if you do the following:
1. Open any project that has been baselined in Microsoft Project.
2. Clear any existing baselines.
3. Click File > Save As and save the project using an alternate name for the import process only.
4. Import the project into Project for the Web.
Do you still get the import error that you reported previously? Please let us know. Thanks!- Geraldine9gOct 17, 2022Copper Contributor
- John-projectOct 12, 2022Silver Contributorsshaffery,
Okay, I'm glad you found a solution.
John