Forum Discussion

BlissL's avatar
BlissL
Brass Contributor
Oct 31, 2022

Approval Center Rules - auto-approve completed tasks

Hi there, 

 

I'm wondering how to set up a rule within the Approval Center that auto approves when team members mark tasks as complete. 

 

However I still want the status updates to go through the Approval Center if the team member is changing the amount of work required for the tasks - 

1 Reply

  • BlissL --

    I am sad to report that you cannot create the Auto Approval Rule you seek. To create the rule you want, the update would need to meet two conditions:

    1. Assignment % Work Complete would need to be 100%.
    2. Assignment Actual Work would need to be less or equal to Assignment Baseline Work.

    Unfortunately, when creating a rule, you can test for one of those two conditions, but not both of them. Sorry, but hope this helps.

Resources