Actual Finish Date field

Hello everybody!

 

How can I track the projected finish date and the actual finish dates in P4TW?  

5 Replies

  • Dino --

    Right now, there is no Actual Finish field available in Project for the Web. To work around this limitation, set the Finish date to when the task actually finished and then mark it as 100% complete. Hope this helps.