Forum Discussion
Dino_Calvinisti
May 01, 2023Copper Contributor
Actual Finish Date field
Hello everybody! How can I track the projected finish date and the actual finish dates in P4TW?
May 02, 2023
Dino --
Right now, there is no Actual Finish field available in Project for the Web. To work around this limitation, set the Finish date to when the task actually finished and then mark it as 100% complete. Hope this helps.
Right now, there is no Actual Finish field available in Project for the Web. To work around this limitation, set the Finish date to when the task actually finished and then mark it as 100% complete. Hope this helps.
daibt
May 02, 2023Brass Contributor
How to track 100% complete and automatic set Finish date when user mark it as 100%
- May 03, 2023daibt --
There is no way to do that in Project for the Web. Sorry.