24/7 resources in Project for the Web

Hello,
in addition to work packages I would like to schedule several production steps in a Project. For this purpose, I have created a resource (3D printer) in Power Apps and set its working time to 24/7. If I now assign an task with a duration of 10 hours to the printer, the effort is set to 26 hours and is also displayed accordingly in the timeline. I don't understand why.

I then tried to set the effort instead of the duration. However, if I enter e.g. 30 hours there, the duration and display in the timeline remains at one day.

 

So the question is: How do I schedule 24/7 resources correctly? Actually, duration and effort should always be the same. Or what do I understand wrong?

 

Julian

5 Replies

  • John-project's avatar
    John-project
    Silver Contributor

    nJulian415 

    First of all how exactly did you set the 3D printer resource's calendar to 24/7? The best way to do that is to simply use the built-in 24 calendar as the Base Calendar for the printer. Assuming the Project Calendar is the default Standard, assigning the printer resource to a 10h task will result in the following:

    Without further details on how you set things up I can't tell why you see a work content of 26 hours.

     

    John

     

    • nJulian415's avatar
      nJulian415
      Copper Contributor

      Thanks, John-project.

      I am working in the web version of Project so things look slightly different. 

      Here's how I set it up:

      • John-project's avatar
        John-project
        Silver Contributor

        nJulian415,
        I'll ask my colleague Dale to jump in on this one. He knows Project for the Web inside and out, I don't.

         

        Update: I contacted Dale and he said that functionality of Project for the Web has never worked correctly. At this point the best I can offer is for you to give feedback to Microsoft via whatever feedback portal there is for PFTW. Understand that PFTW is a work in progress and Microsoft is improving and adding features all the time. You can check out the PFTW roadmap at:

        https://www.microsoft.com/en-ww/microsoft-365/roadmap?filters=Microsoft%20Project

         

        Sorry I can't be of more help.