24/7 resources in Project for the Web
First of all how exactly did you set the 3D printer resource's calendar to 24/7? The best way to do that is to simply use the built-in 24 calendar as the Base Calendar for the printer. Assuming the Project Calendar is the default Standard, assigning the printer resource to a 10h task will result in the following:
Without further details on how you set things up I can't tell why you see a work content of 26 hours.
John
- nJulian415Mar 28, 2023Copper Contributor
Thanks, John-project.
I am working in the web version of Project so things look slightly different.
Here's how I set it up:
- John-projectMar 28, 2023Silver Contributor
nJulian415,
I'll ask my colleague Dale to jump in on this one. He knows Project for the Web inside and out, I don't.Update: I contacted Dale and he said that functionality of Project for the Web has never worked correctly. At this point the best I can offer is for you to give feedback to Microsoft via whatever feedback portal there is for PFTW. Understand that PFTW is a work in progress and Microsoft is improving and adding features all the time. You can check out the PFTW roadmap at:
https://www.microsoft.com/en-ww/microsoft-365/roadmap?filters=Microsoft%20Project
Sorry I can't be of more help.
John- nJulian415Mar 29, 2023Copper Contributor
oh wow, that’s really a bummer. How can such a basic feature not work properly? We‘ll need to switch to a different product then.
thanks anyway, John-project