May 06 2022 10:26 AM - edited May 06 2022 10:26 AM
I need a field to add thedate a task/project etc. is completed. Currently, I see start, and due date but not completion date. Any plans for this?
Thanks
May 10 2022 12:18 AM
@OnuAn The completion date for the tasks is automatically marked by the planner once the task is marked as done. You don't need to manually mark this. To view the task completed date and user, export the Plan to Excel.
May 10 2022 07:08 AM
I@SanthoshB1 That's a false assumption i.e. that the day closed is the completion date given that the task may be closed days after the actual completion date. It would be a good field to have in order to track "actual" completion dates. Thank you for the feedback.
Jun 14 2023 02:03 PM
Yes, this is a necessary feature. As part of any plan understanding due date and completion date is necessary for auditability. Seems odd to have to export to Excel to view and report this level of detail.