Forum Discussion
Tracking Delay Day
- Jun 04, 2020
Kiripong Assuming the left most header cell is in A1, try the following formula in E2 and copy it down.
=MAX(0,TODAY()*(D2="")+(D2*(ISNUMBER(D2))-C2-3))If you want to make it a bit more dynamic, change the REMARKS column to contain the number of days allowed for review only. Then you can can replace the "-3" at the end with "-F2". This would allow for different numbers of review days allowed for different documents.
Riny_van_Eekelen, Sorry to bothering and this question was out of the context yet if you can help that would be awesome and to be more dynamic please see below query:
How to joint text string as per Column C2-C5 base on item A, B , C or D between these 2 tables:
Kiripong Indeed, this is out of context. Better to start a new conversation for in such cases. But never mind. Attached a quick-and-dirty solution for you.