Forum Discussion
Rog778
Dec 03, 2023Copper Contributor
NETWORKDAYS
Hi, I have a Networkdays function error that is confusing me. Number of days calculated are wrong, eg 04/01/2024 07/04/2025 2 Days 14/01/2024 24/01/2024 15 Days There is a column of 11 rows Some a...
Rog778
Dec 03, 2023Copper Contributor
In you picture you posted =NETWORKDAYS would be in cells C2, C3 etc
That's what I don't understand, all it does is calculate the days between two dates, in this your picture A2 B2 and it's still getting then wrong
That's what I don't understand, all it does is calculate the days between two dates, in this your picture A2 B2 and it's still getting then wrong
HansVogelaar
Dec 03, 2023MVP
NETWORKDAYS excludes weekend days (Saturday and Sunday) from the count.