Task List Predecessors SharePoint
Hello I have worked on MS Project and often used Predecessors to link my Tasks and timelines. Task and Sub-Tasks could be Auto scheduled based on Predescessors. I am trying to use the same in ...
Alan Marshall
Jan 14, 2019Iron Contributor
Sync your project file with the SharePoint task list. You can maintain the scheduling in project whilst exposing the tasks to everyone else through the list. The sync is also two way so if a user updates a task progress, when you sync in Project it updates the task