Sharepoint List Business Days auto calculation

Hi,   I'm trying to find a solution that would enable me to calculate an expected completion date in sharepoint list using different sla days, that also takes into account business days only - Mon ...
  • Rob_Elliott's avatar
    Sep 15, 2023

    Kidbaybut the following formula will just take into account Monday to Friday:

    =[Accepted Date]+SLA+ROUNDDOWN(SLA/5,0)*2+IF(WEEKDAY([Accepted Date])+MOD(SLA,5)>=7,2,0)-ROUNDDOWN(WEEKDAY([Accepted Date])/7,0)+IF(AND(MOD(SLA,5)=0,WEEKDAY([Accepted Date])=1),-2,0)+IF(AND(MOD(SLA,5)=0,WEEKDAY([Accepted Date])=7),-2,0)

     

    Rob
    Los Gallardos
    Microsoft Power Automate Community Super User.
    Principal Consultant, SharePoint and Power Platform WSP UK (and classic 1967 Morris Traveller driver)

     

     