how to filter to Progress value "Completed" to Datediff

Hi - I need help with the code to filter Progress value "completed" to eliminate the "Error in Calculation" in other tickets that are not completed yet.     
  • Rob_Elliott's avatar
    Jan 20, 2025

    =IF(ISBLANK([Completed date]),"",DATEDIF([Start date],[Completed date],"d")&" days")

     