Calculate working days in Sharepoint
Hello I want to calculate work days (mon-fri) between to columns in my Sharepoint list. Both columns have date and time. It works for me to calculate days with this formula: "=EndDate-Start...
PradeepKhanna
Jun 25, 2020Copper Contributor
This one did it for me:
=(DATEDIF([Start Date],[End Date],"D"))-INT(DATEDIF([Start Date],[End Date],"D")/7)*2-IF(WEEKDAY([End Date])<WEEKDAY([Start Date]),2,IF(OR(WEEKDAY([End Date])=7,WEEKDAY([Start Date])=1),1,0))+1
I ran it across about 1000 rows in an excel, and the outcome was the same as NETWORKDAYS excel formula across all of them
CoutinhoUK
Aug 26, 2020Copper Contributor
Your formula has worked perfectly for my case, however i was wondering is there is any way to add onto this formula a list of bank holidays days like in Excel with Networking days.