widgets per day
Hello, I have a task to produce 1000 widgets, and I know that I can produce 10 widgets per day. Do I need to enter my duration as 1000 days and add a resource at 1000%, or is there a more intuitive way to enter my task duration based on widgets instead of days? The problem I have is that once I do this, the duration changes to 100 days, but now I have nothing to remind me that I need to produce 1000 widgets. Once things start changing, this is very difficult to keep track of. Is there a way to just enter total widgets, and add resources for widgets per day, and let Project calculate the duration?
- Robert --
Duration is the time span during which the work will take place on a task. In your scenario, the Duration would be 100 days. There is no way to enter the total number of widgets other than adding a note to the task. Assign the resource at 100%, assuming the resource must work full-time to complete the task. Hope this helps.
- Robert --
Duration is the time span during which the work will take place on a task. In your scenario, the Duration would be 100 days. There is no way to enter the total number of widgets other than adding a note to the task. Assign the resource at 100%, assuming the resource must work full-time to complete the task. Hope this helps.