widgets per day

Hello, I have a task to produce 1000 widgets, and I know that I can produce 10 widgets per day.  Do I need to enter my duration as 1000 days and add a resource at 1000%, or is there a more intuitive ...
  • Dale_HowardMVP's avatar
    Jun 07, 2022
    Robert --

    Duration is the time span during which the work will take place on a task. In your scenario, the Duration would be 100 days. There is no way to enter the total number of widgets other than adding a note to the task. Assign the resource at 100%, assuming the resource must work full-time to complete the task. Hope this helps.