Forum Discussion
RobertOrnelas
Jun 07, 2022Iron Contributor
widgets per day
Hello, I have a task to produce 1000 widgets, and I know that I can produce 10 widgets per day. Do I need to enter my duration as 1000 days and add a resource at 1000%, or is there a more intuitive ...
- Jun 07, 2022Robert --
Duration is the time span during which the work will take place on a task. In your scenario, the Duration would be 100 days. There is no way to enter the total number of widgets other than adding a note to the task. Assign the resource at 100%, assuming the resource must work full-time to complete the task. Hope this helps.
Jun 07, 2022
Robert --
Duration is the time span during which the work will take place on a task. In your scenario, the Duration would be 100 days. There is no way to enter the total number of widgets other than adding a note to the task. Assign the resource at 100%, assuming the resource must work full-time to complete the task. Hope this helps.
Duration is the time span during which the work will take place on a task. In your scenario, the Duration would be 100 days. There is no way to enter the total number of widgets other than adding a note to the task. Assign the resource at 100%, assuming the resource must work full-time to complete the task. Hope this helps.