Unable to reset up a field value in Project details

Hi Community,

I have created an enterprise custom lookup table, the used it inside a custom field.

By mistake, in the Project details page, I selected a value from that field and saved the report while I should have kept it empty.

The problem is I am unable to reset the field and keep it empty though the custom field was configured as not required.

 

Any suggestions to solve this issue?

  • Knowledgeseeker --

    Open and check out the project from the Project Center page in PWA and then display the Project Details PDP. Click the Select Value button (the ... button) to the right of the field in which you selected the wrong value. In the pick list that appears, click the name of the wrong value you previously selected. This action will CLEAR the wrong value and return the field to a blank value. I know that this is NOT very intuitive, is it? Hope this helps.

1 Reply

  • Knowledgeseeker --

    Open and check out the project from the Project Center page in PWA and then display the Project Details PDP. Click the Select Value button (the ... button) to the right of the field in which you selected the wrong value. In the pick list that appears, click the name of the wrong value you previously selected. This action will CLEAR the wrong value and return the field to a blank value. I know that this is NOT very intuitive, is it? Hope this helps.