Forum Discussion

ThuTrang1405's avatar
ThuTrang1405
Copper Contributor
Aug 17, 2023

Unable to import the project into Project for the Web because the project duration exceeds 3650 days

I have an MPP file like the image below. There is a summary task with a duration of 1583 days, while the duration limit of MS Project for the Web is 3650 days. However, when I import this project into MS Project for the Web, it indicates that it's not accepted due to the project duration exceeding 3650 days. Could you please help me identify where the issue might be or if there is a way to resolve this?
Thanks~

3 Replies

Resources