Forum Discussion
ThuTrang1405
Aug 17, 2023Copper Contributor
Unable to import the project into Project for the Web because the project duration exceeds 3650 days
I have an MPP file like the image below. There is a summary task with a duration of 1583 days, while the duration limit of MS Project for the Web is 3650 days. However, when I import this project int...
RodFromm
Aug 18, 2023Iron Contributor
Review the P4W project boundaries in the link below and see if your project exceeds any of those limits? If it does, correct those issues and try the import again.
https://learn.microsoft.com/en-us/office365/servicedescriptions/project-online-service-description/project-web-service-description#project-for-the-web-boundaries
https://learn.microsoft.com/en-us/office365/servicedescriptions/project-online-service-description/project-web-service-description#project-for-the-web-boundaries