Forum Discussion

JeanineB007's avatar
JeanineB007
Copper Contributor
Aug 16, 2024

Tracking Ghant -tracking view. % complete planned column

Pls assist I need to add a column to show the % that was planned (ie Baseline % ??on the tracking ghant in tracking Form.  (it only % complete on current updating

  • John-project's avatar
    John-project
    Silver Contributor
    JeanineB007,
    Okay, but first you will have to define exactly what you mean by "planned % complete". Percent complete is the ratio or actual duration to duration and those are the fields used by Project to calculate the % Complete value.

    Some options are: Actual Duration compared to Baseline Duration, Baseline Start to Status date compared to Baseline Duration, or something else.

    And what exactly is the "tracking Form"?

    John

Resources