Tracking Ghant -tracking view. % complete planned column
Pls assist I need to add a column to show the % that was planned (ie Baseline % ??on the tracking ghant in tracking Form. (it only % complete on current updating
- John-projectSilver ContributorJeanineB007,
Okay, but first you will have to define exactly what you mean by "planned % complete". Percent complete is the ratio or actual duration to duration and those are the fields used by Project to calculate the % Complete value.
Some options are: Actual Duration compared to Baseline Duration, Baseline Start to Status date compared to Baseline Duration, or something else.
And what exactly is the "tracking Form"?
John