Forum Discussion
JeanineB007
Aug 16, 2024Copper Contributor
Tracking Ghant -tracking view. % complete planned column
Pls assist I need to add a column to show the % that was planned (ie Baseline % ??on the tracking ghant in tracking Form. (it only % complete on current updating
John-project
Aug 16, 2024Silver Contributor
JeanineB007,
Okay, but first you will have to define exactly what you mean by "planned % complete". Percent complete is the ratio or actual duration to duration and those are the fields used by Project to calculate the % Complete value.
Some options are: Actual Duration compared to Baseline Duration, Baseline Start to Status date compared to Baseline Duration, or something else.
And what exactly is the "tracking Form"?
John
Okay, but first you will have to define exactly what you mean by "planned % complete". Percent complete is the ratio or actual duration to duration and those are the fields used by Project to calculate the % Complete value.
Some options are: Actual Duration compared to Baseline Duration, Baseline Start to Status date compared to Baseline Duration, or something else.
And what exactly is the "tracking Form"?
John