Timesheet Project Web App - Problem with hours/day

Hello everyone,

 

I don't understand why the number of hours per day in my tasks in timesheets in Project Web App is 7h per day inspite of the number of hours per day in my project's options (in MS Project) is 8h/day and also 8h/day in "Timesheet Settings and Defauts"...


Could someone explain that to me?

Thanks you very much in advance !

1 Reply

  • Gert-Jan_JSR's avatar
    Gert-Jan_JSR
    Copper Contributor

    Hi Colin,

     

    Could it be that the resource is available for less than 100% of his time or has a resource calendar setting of 7 working hours per day? 

     

    Could you provide a screenshot of the information in the task usage view for this task and period?