Forum Discussion
Colin_Besserer
Dec 18, 2018Copper Contributor
Timesheet Project Web App - Problem with hours/day
Hello everyone, I don't understand why the number of hours per day in my tasks in timesheets in Project Web App is 7h per day inspite of the number of hours per day in my project's options (in MS...
Gert-Jan_JSR
Feb 12, 2019Copper Contributor
Hi Colin,
Could it be that the resource is available for less than 100% of his time or has a resource calendar setting of 7 working hours per day?
Could you provide a screenshot of the information in the task usage view for this task and period?