Forum Discussion

CarlosMorenoV's avatar
CarlosMorenoV
Copper Contributor
May 10, 2023

Task link visibility: OK in Desktop client but not visible in Online

I am very upset because I don't see how to activate visibility of task links (connection lines) in Project Online ).  See attached screenshot.

Tasks are effectively linked, and you can see perfectly at Desktop client but any Gantt view in Online(PWA) -same published project-  show them. (neither other projects I have published).

 

I have even changed screen resolution, looked for PWA server configuration,.... no more ideas.

 

Some old screenshots I have from same projects existed in an old Project Server show task links with light blue color.

 

I would appreciate your kind help.

Thanks a lot for your attention.

 

 

 

 

 

7 Replies

  • Hello CarlosMorenoV ,

    I've not seen that before, can you add the predecessors column in the view (PWA Settings > Manage Views > Select your view > add Predecessors > Save), do you see values there? Here is my test project project:

     

    Paul

    • CarlosMorenoV's avatar
      CarlosMorenoV
      Copper Contributor

      Paul_Mather 

       

      Hi Paul, here I have included Predecessors column.  Moreover, same project shows link lines perfect in Desktop client.

      Any idea?.  Thank a lot for your help !!.

      Carlos,

       

       

      • Paul_Mather's avatar
        Paul_Mather
        MVP

        Hello CarlosMorenoV ,

        Is it just this one project that has the issue? Do other projects display the links OK? What about changing views in the schedule PDP, do they all show the same for this project?

        Paul