Forum Discussion
jatupol999
Jul 13, 2023Copper Contributor
task and timesheet on user not show
Project manager assign task ms project online to user but task and timesheet on user not show that task . Project manager check. at resource assigments that show send already to user . I test sent task to 3 user same problem . how to check
7 Replies
- RatanPushpBrass Contributor
By default, current week tasks are displayed in Task and Timesheet. Could you please check assignment dates.
- jatupol999Copper Contributor
check already assigment ok Which is to focus for set pwa
- RodFrommSteel Contributor
Tasks do not always just appear in the timesheet as they should. Try step 1 below. If that doesn't work there is something with the task that is not setup correctly.
- Have user open their timesheet and try the following.
- On the ribbon select OPTIONS and ensure they don't have a filter set.
- On the ribbon select TIMESHEETS, click Add Row the select 'Select from Existing Assignments'. A dialog will appear. The user can drill down and select the missing task(s) then click OK to add them to their timesheet.
- Ensure the timesheet is not in Approved status. If it is once they Recall it they should repeat the previous step. (this is rare, but I've seen it happen)
- Open project plan
- Ensure the task field Locked = No
- Check assignments dates as mentioned previously as they must intersect with the timesheet dates
- Check Build Team and ensure the Booking Type = Committed (this is rare, but I've seen it happen)
- jatupol999Copper ContributorI checked alrerady . but i not had the task field Locked
Which is to focus for set pwa. ?
- Have user open their timesheet and try the following.