Forum Discussion
task and timesheet on user not show
By default, current week tasks are displayed in Task and Timesheet. Could you please check assignment dates.
Tasks do not always just appear in the timesheet as they should. Try step 1 below. If that doesn't work there is something with the task that is not setup correctly.
- Have user open their timesheet and try the following.
- On the ribbon select OPTIONS and ensure they don't have a filter set.
- On the ribbon select TIMESHEETS, click Add Row the select 'Select from Existing Assignments'. A dialog will appear. The user can drill down and select the missing task(s) then click OK to add them to their timesheet.
- Ensure the timesheet is not in Approved status. If it is once they Recall it they should repeat the previous step. (this is rare, but I've seen it happen)
- Open project plan
- Ensure the task field Locked = No
- Check assignments dates as mentioned previously as they must intersect with the timesheet dates
- Check Build Team and ensure the Booking Type = Committed (this is rare, but I've seen it happen)
- jatupol999Jul 17, 2023Copper ContributorI checked alrerady . but i not had the task field Locked
Which is to focus for set pwa. ?- RodFrommJul 17, 2023Steel ContributorIf Locked field allows the PM to control whether a task is displayed in timesheet. If Locked = Yes the task will not be displayed in anyone's timesheet.
- jatupol999Jul 17, 2023Copper Contributor
The last time project manager can sent task user can receive done but now when edit name in task and edit resource name (005,009) of user testmail2 kup then sent save publish again and assign resource name 0002 ,027,029 then sent save publish then found problem per question this issue user not see task ( I test other 2 user .. same problem )
I think set pwa ? or any data ? please help for me ? you can remote for fix ? or any check ?
picture task user testmail2 kup
resource assigment from project manager log send to user already
at project center