Forum Discussion
Talo71
Jul 18, 2022Copper Contributor
Set automatic dependencies between different tasks of the same resource
Hi,
Is there an option to configure MS Project so that it will automatically set a dependency between tasks that are assigned to a given resource?
We want to avoid the need to manually search the resource's last task and then manually set a dependency between that task and the next one.
Sample:
Resource Danny has a tasks that is scheduled to be finished on July 20th.
We want that Danny's next task will automatically begin on July 21st and not on the project's start date.
Is that possible?
Thanks,
- John-projectSilver ContributorTalo71,
The simple answer to your question is "no". In Project dependencies are between tasks, independent of when a resource is available.
The process of setting up a plan is to define what needs to be done (tasks), set up dependencies between those tasks to form a logical sequence of execution to reach an end goal. Once that is in place, appropriate resources are assigned to accomplish each task. If after assigning resources, overallocation occurs (i.e. a resource is assigned for more hours than that resource's max units), Project will indicate that with a "red" man symbol. The project manger can then manually adjust assignments or use Project's leveling functionality to help alleviate overallocations.
Project does not optimize the plan, there are just too many variables to make that a feasible option.
John- Talo71Copper Contributor
John-project Thank you
- John-projectSilver Contributor
- Ignacio_MartinIron ContributorHi, As John says, resource leveling is the usual option to solve what you ask. Regards.