Save as a current project to a Project template via Teams Channel

Premium Office 365 for Workplace and Project is available under the Teams channel.

I have my current project ready for future projects, and have been trying to create a template, but I could not find the option to save the existing project file structure only.

Even though, I save as a copy this with a different name, the copied file works as the original file.

I got the same damage on my original Project file after some cleanup in the copied file.

There is no UNDO option.

I have looked up this Help section about it, but it says I could find a Save As under File, but my Project file under Teams Channel does not have this function.

As you see above, there is no option like I guess the Desktop version might have.

Even in my Web version does not show File tab.

 

Please advise.

 

Thank you.

  • Hello ujsang ,

    I think you are probably reading a guide for Project Desktop. In Project for the web / Planner Premium, you have the "Copy Plan" feature.

    Paul

3 Replies

  • ujsang's avatar
    ujsang
    Copper Contributor

    Paul,

    Appreciate your reply.

    I tried both, but the COPY PLAN makes the same file just duplicated, and they are tied together like one file; even though I changed the subject of the new copied one and date, all changes affect the original file. I learned this the hard way and lost some of my work. 

    Please advise if you see otherwise.

    Thank you.

  • RodFromm's avatar
    RodFromm
    Steel Contributor

    Microsoft hasn't enabled the ability for you to create new a template or template from an existing plan.  I doubt you will ever see this the default environment, but hopefully we will see it in named environment in the not so distance future.

  • Hello ujsang ,

    I think you are probably reading a guide for Project Desktop. In Project for the web / Planner Premium, you have the "Copy Plan" feature.

    Paul